Construction of expressway S69 started in year 1999.
Section S69 Laliky II is 1,26 km long.
There is Laliky interchange.
Part of this first section of the S69 with length 1,1 km was opened to traffic in half-profile in year 2000.
Section S69 Zwardon - Myto is 1,35 km long.
The work on expressway was completed in December 2004 and was opened to traffic on 16 January 2006.
Section S69 | Length km |
Comment |
(D2) Myto - Zwardoń | 1,35 | full profile 1,2 km, opened to traffic 1/2006 |
(D1) Zwardoń - Laliki II | 1,794 | 1/2 profile, opened to traffic 12/2008 |
(C3) Laliki II | 1,257 | 1/2 profile, 1,1 km opened to traffic in year 2000 |
(C2) Laliky - Szare | 4,676 | 1/2 profile, opened to traffic 3/2010 |
(C1) Szare - Milówka | 2,305 | 1/2 profile, opened to traffic 1/2007 |
(B) Milówka - Przybedza | 8,164 | 1/2 profile, construction 2015-2018 |
(A2) Przybedza - Browar | 4,865 | 1/2 profile, opened to traffic 1/2007 |
(A1) Browar - Żywiec | 4,645 | 1/2 profile, part of S69 2,8 km + feeder Żywiec, opened to traffic 1/2007 |
Żywiec - Żywiecka/Bystrzańska(Mikuszowice) | 15,56 | full profile, under construction 8/2010 - 2013 |
Żywiecka/Bystrzańska(Mikuszowice) - Krakowska | 5,25 | full profile, opened to traffic 10/2011 |
S1 a S69 Krakowska - Rosta | 3,85 | full profile, opened to traffic 10/2011, section S1 and S69 |
S1 Rosta - Komorowice | 2,85 | full profile, opened to traffic 8/2011, section S1 |
This page was last modified on March 23, 2013